Search

Update on Construction Progress at the Paul and Diane Manning Institute of Biotechnology

June 11, 2025 by jta6n@virginia.edu

Construction is progressing on the Paul and Diane Manning Institute of Biotechnology at the Fontaine Research Park. All underground plumbing and electrical work were completed and inspected, allowing the concrete slab on grade to be poured in April 2025.

The project is closely sequenced by the project team to encourage crew efficiency. While this first steel column was being set, concrete pours were continuing at the North Tower. In early June, steel installation of the North Tower commenced.

Work is also progressing on several other construction projects at the Fontaine Research Park. Below aerial photos show progress on the Fontaine Central Energy & Utility Plant, the new traffic circle at the entrance of Fontaine Research Park, and the Fontaine Parking Garage.

Filed Under: Research